General update:
- Major deliveries now occur within the confines of the fence line
- Night security is in effect from 10:00 pm to 6:00 am
- It is anticipated that Grafton Street will be reinstated for construction use by the end of June
What’s coming up in June:
- Ongoing structural steel installation on levels 4-7
- Pouring concrete and erecting the supports for the balance of level 5, 6, 7 and 8
- Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout June, July and August
Notice to neighbours:
- Sidewalk closures around construction site are still in effect
- Expect daily concrete truck activity and increased noise during construction at street level
- Intermittent street closures around the site perimeter for formwork removal throughout concrete construction
- Prince, Market and Argyle Street closures to occur before 10:00 am