General Updates:

  • The curtain wall on the hotel and lower levels of the Grafton and Sackville sections are near complete.
  • The process of laying exterior brick has begun, starting with the hotel tower face first in order to remove the current scaffolding towers. 
  • Construction is underway in the Convention Centre. The lower levels (in some area) are ready for final finishes. 
  • Coolers and freezers for the Convention Centre kitchen are now on-site.
  • The North Tower elevator bank is nearing completion. 
  • NSP work is ongoing in the 3rd electrical vault, with plans for the vault to be energized sometime in late October or November.