General update:

  •  Construction of level 15 of the office tower is complete and construction of level 16 is underway. Construction of level 16 of the hotel tower is underway.
  • Major deliveries continue to occur within the confines of the fence line.
  • Full time, 24/7 security is now in effect. Site-wide video surveillance is being purchased and installed.
  • The project site workforce is approximately 150. This is expected to reach upwards of 300 by Christmas.
  • To date, nearly 37,000 cubic metres of concrete have been poured.
  • The structure is about 55m/182ft above Argyle Street.
  • Sackville Street will be closed for most of November.

What’s coming up in November:

  •  Winter condition construction hoarding will be installed around the perimeter.
  • Glass installation on the north tower will continue into 2016.
  • Ongoing structural steel installation of the Convention Centre will be nearing completion.
  • Pouring concrete for landscape walls around the perimeter will be ongoing throughout November.

 Notice to neighbours:

  • Sidewalk closures around the construction site remain in effect.
  • Expect daily truck activity and increased noise during construction at street level.
  • Intermittent street closures around the site perimeter for form work removal during concrete construction are expected.
  • Waterline work along Sackville, Market and Prince Streets is tentatively scheduled to begin in November.