General update:

  • Concrete for the balance of level 3 is complete
  • The erection of the fourth crane is complete
  • Night security is in effect from 10 pm to 4:30 am
  • Construction is planned to reach Market Street by the end of November
  • It is anticipated that Grafton Street will be reinstated for construction use by the end of November

What’s coming up in November:

  • Pouring concrete for the balance of level 4 and 5
  • Ongoing structural steel installation
  • Installation of concrete encased duct banks for electrical wiring
  • Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout November

Notice to neighbours:

  • Sidewalk closures around construction site are still in effect
  • Expect daily concrete truck activity and increased noise during construction at street level
  • Businesses will be notified 5 days in advance of the following anticipated street closures:
    • Argyle Street will close between Prince and Sackville Streets. Traffic will be redirected via Prince, Brunswick and Sackville Streets
    • Sackville Street will close at Grafton Street. Traffic will be redirected via Market, Blowers and Barrington Streets