General update:

  • Major deliveries now occur within the confines of the fence line
  • Night security is in effect from 10:00 pm to 6:00 am
  • It is anticipated that Grafton Street will be reinstated for construction use by the end of May

What’s coming up in May:

  • Ongoing structural steel installation on levels 4-7
  • Pouring concrete and erecting the supports for the balance of level 5, 6 and 7
  • Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout May

Notice to neighbours:

  • Sidewalk closures around construction site are still in effect
  • Expect daily concrete truck activity and increased noise during construction at street level
  • Intermittent street closures around the site perimeter for formwork removal throughout concrete construction
  • Argyle Street closures to occur before 10:00 am