General update:

  • Major deliveries now occur within the confines of the fence line
  • Night security is in effect from 10:00 pm to 6:00 am
  • It is anticipated that Grafton Street will be reinstated for construction use by the end of March

What’s coming up in March:

  • Pouring concrete for the balance of level 3, 4, 5 and 6
  • Structural steel installation on level 3 and 5
  • Erecting the supports for level 6
  • Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout March

Notice to neighbours:

  • Sidewalk closures around construction site are still in effect
  • Expect daily concrete truck activity and increased noise during construction at street level