General Updates:

  • Brick and glass window installation on the hotel tower is now complete. 
  • Brick work along Prince Street is underway.
  • Man and material hoists have been removed from the office tower.
  • Nova Scotia Power vault & underground work is 100% complete.
  • Interior steel stairs have been installed.
  • The Multi Function Room has been equipped with operable wall tracks.
  • The permanent gas hookup is now in place.
  • Flooring has been finalized and ordered.
  • Ceiling rough ins are being done for M&E services.
  • Drywall work is underway.
  • Interior wall panels are currently being fabricated in Italy and are likely to arrive next month.
  • There is an average of 185 workers on site daily. 

Upcoming:

  • Starting next month, ground level retail entrances will begin to be constructed. This phase of work was re-evaluated to simplify and make the entrances tie seamlessly to the overall building scheme.