General update:

  • Construction has reached Market Street
  • Major deliveries now occur within the confines of the fence line
  • Night security is in effect from 10:00 pm to 6:00 am
  • It is anticipated that Grafton Street will be reinstated for construction use by mid-February
  • New sanitary storm water lines have been installed along Argyle Street
  • Installation of girders that support the balance of Grafton Street is complete

What’s coming up in January:

  • Pouring concrete for the balance of level 3, 4, 5 and 6
  • Erecting the supports for level 6
  • Ongoing structural steel installation
  • Installation of concrete encased duct banks for electrical wiring
  • Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout January

Notice to neighbours:

  • Sidewalk closures around construction site are still in effect
  • Expect daily concrete truck activity and increased noise during construction at street level
  • Businesses will be notified 5 days in advance of the following anticipated street closures:
    • Sackville Street will close at Grafton Street. Traffic will be redirected via Market, Blowers and Barrington Streets