Ongoing Activity

  • Sidewalk closures around the construction site continue to be in effect.
  • Drilling for shoring installation (within the site perimeter) is ongoing.
  • The lagging installation for the shoring ongoing
  • Shoring tie-back installation ongoing
  • Trucking material offsite ongoing
  • Drilling and blasting rock ongoing
  • Line drilling around the perimeter of the site has begun

Upcoming Activity

  • Drilling and installation of rock anchors to beginĀ at the end of next week