General Update:
-
The exterior glazing on the office tower is nearing completion, with two floors left to be done.
-
The roofing is near complete on the ballroom section.
-
The 1st floor mechanical room is almost complete. There are mechanical rooms on L6 and a main mechanical room on L 7.
-
The escalators are all in place now.
-
The steel stud framing and mechanical and electrical rough-ins are underway on L1 and L2.
Fun Fact:
- There are approximately 200 workers on site, with the number of workers expected to double by May 2016.
What's Coming Up:
-
The glass for the hotel section will be arriving in early May.
-
It is anticipated that the following areas will be enclosed by:
-
May 18th – Office Towers
-
July 16th – Convention Centre
-
September 16th – Hotel Towers
-