General update:

  • Major deliveries now occur within the confines of the fence line
  • Night security is in effect from 10:00 pm to 6:00 am
  • It is anticipated that Grafton Street will be reinstated for construction use by the end of April

What’s coming up in April:

  • Pouring concrete for the balance of level 5, 6 and 7
  • Structural steel installation on level 3 and 5
  • Erecting the supports for level 6
  • Relocation of the fence line along the site perimeter of Prince, Sackville and Market Streets will be carried out sequentially throughout April

Notice to neighbours:

  • Sidewalk closures around construction site are still in effect
  • Expect daily concrete truck activity and increased noise during construction at street level
  • Market Street will be closed on April 12, reopening on April 13